AU Compliance AI

AU Compliance AI · Guide

CodeMark: The Application Flow, and the One Decision That Sets the Bill

Last verified: 2026-06-14中文版 →

CodeMark is the pathway for building products used under the National Construction Code: cladding, linings, insulation, waterproofing, structural components. If your product goes into the wall, roof or structure of an Australian building, this is usually the scheme.

The process itself is not complicated — five phases, each with a document set and an output. What costs people money is a judgement made before Phase 1 even starts, and it is the one this guide leads with.

Verified facts this guide rests on

In a building required to be of Type A or Type B construction, external walls including the facade covering, framing and insulation must be non-combustible under NCC 2025 Volume One Clause C2D10. The Deemed-to-Satisfy evidence is an AS 1530.1 test result from an Accredited Testing Laboratory, or the material being one of the items deemed non-combustible by C2D10(5).
Source: NCC 2025 Volume One Clause C2D10; AS 1530.1:2024 · last verified 2026-06-14
AS 5113 full-scale external wall classification testing is not a mandatory NCC requirement. It is referenced through NCC 2025 Volume One Verification Method C1V3 as one acceptable Performance Solution route for limiting fire spread via external walls, and an applicant taking the Deemed-to-Satisfy path under C2D10 does not need an AS 5113 test.
Source: NCC 2025 Volume One Verification Method C1V3; AS 5113:2016 · last verified 2026-06-14
Under NCC 2025 Volume One Clause C2D15, externally located bonded laminated cladding panels in Type A or Type B construction must have all layers mechanically supported or restrained to the supporting frame. Chemical adhesion alone is not acceptable, and a short list of products is exempt under C2D15(2).
Source: NCC 2025 Volume One Clause C2D15 · last verified 2026-06-14

For external walls: the decision that sets the bill

In a building required to be of Type A or B construction, external walls — the facade covering, the framing and the insulation — must be non-combustible under NCC 2025 Volume One Clause C2D10. The Deemed-to-Satisfy evidence is an AS 1530.1 test result from an Accredited Testing Laboratory, or the material being one of the items C2D10(5) deems non-combustible.

AS 5113 full-scale external wall classification testing is not a mandatory NCC requirement. It is referenced through Verification Method C1V3 as one acceptable Performance Solution route for limiting fire spread via external wall assemblies. If you take the Deemed-to-Satisfy path under C2D10, you do not need an AS 5113 test.

One more clause worth knowing before you design the system: under C2D15, externally located bonded laminated cladding panels in Type A or B construction must have all layers mechanically supported or restrained to the supporting frame. Chemical adhesion alone is not acceptable. A short list of products is exempt under C2D15(2) — laminated glass systems, layered plasterboard, fibrous-plaster sheet, fibre-reinforced cement sheeting, perforated gypsum lath, and garage-door components.

Is CodeMark even the right scheme?

  • Plumbing and drainage products go to WaterMark, not CodeMark. Routing them here is the single most common wrong-pathway mistake.
  • Electrical and electronic equipment goes to RCM, and to EESS where the equipment is in scope.
  • A building product already fully covered by a Deemed-to-Satisfy provision, where nobody in the supply chain is asking for independent certification, may not need CodeMark at all.
  • CodeMark earns its keep when the product is innovative or non-traditional, when you want one nationally recognised mark instead of arguing state by state, or when the building certifier wants evidence for a Performance Solution.

The five phases

  1. Pre-assessment. Lock down the pathway, the applicable standards with their editions, the target NCC clauses and the scope — before spending anything on testing. Bring a one-to-two page product brief stating exact use and materials, your target states, any existing test reports, and an English technical data sheet. What you should get back is a scope statement, a standards list with editions, a test plan, a factory audit plan and a firm quote.
  2. Testing. Confirm the current edition of every applicable standard first — an obsolete edition is a rejection, not a discussion. Use a NATA-accredited laboratory in Australia or an ILAC MRA-recognised one offshore, check whether any standard requires certifier-witnessed testing, and reserve budget for a re-test.
  3. Document review and factory audit. The technical file wants test reports, quality-system documentation, a process flow with QC checkpoints, material data and supplier traceability, English installation instructions, and a declaration that the formulation is complete — no undisclosed fire retardants or stabilisers. The audit runs on-site at every manufacturing location.
  4. Certificate issue and listing. Read the draft certificate’s scope statement word for word against the product variants, applications and limitations you actually intend to supply. Then verify your listing appears on the JAS-ANZ register.
  5. Maintenance and surveillance. Annual surveillance re-checks that the quality system, process, materials and traceability still match the certified scope. Any change of formulation, substrate, adhesive, coating, factory location or requested NCC clause coverage needs an Extension of Scope before the changed product is sold.

What the cost and duration figures are worth

Put those ranges next to the AS 5113 figure and the shape of the problem is clear: everything in the ordinary flow lives in the thousands to low tens of thousands. One avoidable test decision on an external wall product can exceed the entire rest of the programme.

What this means if you manufacture outside Australia

  • Settle the compliance path — Deemed-to-Satisfy or Performance Solution — in pre-assessment, in writing, before any test is commissioned. This is the highest-leverage hour in the whole project.
  • Standard editions are a rejection trigger, not a formality. Get the edition list in writing from the certifier and hand that list to the laboratory.
  • Every manufacturing location is audited on site, and offshore audits carry auditor travel. Declare all sites at application stage rather than after a certificate exists.
  • The most common audit failure is not a broken process — it is floor staff who cannot describe the written procedure. Run an internal mock audit two weeks ahead and book a translator if English is not the site standard.

Frequently Asked Questions

Do I need an AS 5113 test for cladding on a building over three storeys?

Not as a matter of the NCC. AS 5113 is referenced through Verification Method C1V3 as one acceptable Performance Solution route. If the product takes the Deemed-to-Satisfy path under C2D10 — non-combustibility evidenced by AS 1530.1, or the material being deemed non-combustible by C2D10(5) — no AS 5113 test is required. Given the cost gap, settle which path applies before commissioning anything.

Is CodeMark mandatory?

CodeMark is a voluntary scheme that produces evidence of NCC compliance which building certifiers across all states recognise. What is mandatory is compliance with the NCC itself. CodeMark is one way of evidencing it — often the practical one for an imported or non-traditional product, because the alternative is re-arguing the case with each certifier.

Can testing be done in China?

Offshore testing is acceptable from a laboratory recognised under the ILAC Mutual Recognition Arrangement; NATA accreditation is the Australian equivalent. Confirm the laboratory’s status and the exact standard edition with the certifier before samples ship, and check whether any test needs to be witnessed.

We changed the adhesive but the panel is the same. Does the certificate still cover it?

No. A change of formulation, substrate, adhesive, coating or factory location needs an Extension of Scope before the changed product is sold. Certification tracks a configuration, not a product name.

The certificate is national. Why did QLD reject our product?

A CodeMark certificate evidences NCC compliance; states can adopt the NCC with variations and add their own requirements. NSW, QLD and VIC diverge most. Raise your target states in pre-assessment so the scope statement addresses them, and keep tracking state adoption of NCC amendments.

Not sure if your product is in scope?

Run the free pre-check — map your product to AS/NZS standards and see your main rejection risks in under 2 minutes.

Free Pre-Check →